Application Notes

无线 PPM 套件
Challenge: Identify and correct the source of reduced output in one of multiple production lines. A water bottling operation had five steps in its bottling process: Cleaning, Filling, Capping, Labeling, and Packaging. One of the plant’s production lines had a recurring problem of lower output than the other lines. The production manager wanted to identify the step, causing bottling constraints and quantify losses in the underperforming line in order to determine how to bring output up to that of the other lines. The bottling machine in question was older and had no way to monitor throughput.